Skip to content
Commercial Solar Surveys

Commercial solar feasibility study

A feasibility study answers one question before you spend money: will solar PV on this site work, and will it pay? Here is what a proper study covers, the difference between a desktop check and an on-site survey, and the outputs you should expect to see.

What a feasibility study is for

A commercial solar feasibility study is the piece of work that turns "we have a big roof and high bills" into a decision you can take to a board, a landlord or a finance provider. It should tell you how big a system the site can take, how much electricity it will generate, how much of that you will use, what it will save, what it will cost and what could get in the way.

A good study is honest about the negatives. Some roofs are too old, some supplies are too small, some buildings use most of their power at night. Finding that out before you commit is the whole point. A study that only ever says yes is a sales brochure, not a feasibility study.

It also sits at the front of a sequence. The study tells you whether to proceed, the roof survey and structural survey confirm the building can carry the system, the G99 application secures the grid connection, and only then does an installer finalise the design and price.

Desktop assessment versus on-site survey

Feasibility work usually starts at a desk and ends on the roof. Both stages have a place, and it helps to know what each can and cannot tell you.

Desktop assessment On-site or virtual survey
Based on Satellite and aerial imagery, address data, your bills or half-hourly data A visit to the roof and electrical intake, or a guided video walkround
Good for Rough system size, likely yield, a first view of savings Roof condition, access, fragile areas, cable routes, the main switchboard
Cannot see Roof condition, hidden shading, the state of the electrics, asbestos Long-term structural capacity without an engineer's calculations
Typical output An indicative size and payback range A firm proposed layout, risks list and the information needed to quote

A desktop check is quick and cheap to produce, but it is only as good as the assumptions behind it. If it has not looked at your actual consumption, the savings figure is a guess. The on-site or virtual stage is where most of the real risks are found.

What goes into the study

Your energy use

The single biggest driver of payback is how much of the generated electricity you use on site rather than export. That depends on when you use power, not just how much. Annual totals from bills give a starting point; half-hourly data shows the shape of your demand through the day, the week and the year. Our page on energy data analysis explains what the study looks for.

The roof or land

Usable area, orientation, pitch, shading, covering type, age and condition all affect how many panels fit and how well they perform. A typical UK rooftop array produces roughly 800 to 1,050 kWh per kWp per year, higher in southern England and lower in northern England and Scotland. East-west layouts on flat roofs produce less per kWp but fit more panels, which can mean more generation overall. If the roof is unsuitable, the study should look at alternatives such as ground-mounted arrays or solar carports.

The electrical supply and grid

The study needs to know your supply capacity, the rating of the main switchboard, where panels would connect and whether the local network can accept the output. Anything above the small G98 limit needs approval from your Distribution Network Operator under G99, and the answer can shape the whole project.

The outputs you should expect

A useful feasibility study gives you these, in plain numbers with the assumptions written down:

  1. Proposed system size in kWp, with a draft layout showing which roof areas are used and why others are excluded.
  2. Yield model: expected annual generation in kWh, ideally month by month, with the orientation, pitch, shading and degradation assumptions stated.
  3. Self-consumption and export split: how much of the generation you are expected to use on site, based on your demand profile.
  4. Savings: the value of on-site use at your own unit rate, plus export income where a Smart Export Guarantee tariff or other export arrangement applies.
  5. Indicative cost and payback: an installed cost range, a simple payback period and, where useful, a longer-term view over the panel warranty period.
  6. Grid position: whether G98 or G99 applies, whether export limitation is likely to be needed, and any known network constraints.
  7. Risks and unknowns: roof condition, structural questions, asbestos, planning, landlord consent, long cable runs, access costs.
  8. Next steps: what has to happen, in what order, before a firm quote can be given.

If any of those are missing, ask why. The commercial solar survey checklist is a useful prompt list.

A worked example (illustrative)

Take a 100 kWp rooftop system at an illustrative £900 per kWp, so about £90,000 excluding VAT. At 900 kWh per kWp it generates about 90,000 kWh a year. If 80% is used on site at an illustrative 24p per kWh, that saves about £17,280. The other 20% exported at an illustrative 5p per kWh brings in about £900. That is roughly £18,180 a year before maintenance, giving a simple payback of about 5 years before any tax relief.

Change one assumption and the answer moves. If the building is empty at weekends and only 55% is used on site, the annual benefit drops noticeably and the payback stretches. That is why a study built on your real consumption is worth far more than one built on averages. Our solar payback guide walks through the sensitivities, and the commercial solar cost page explains what moves the price per kWp.

Risks a good study flags early

  • A roof near the end of its life. Panels last 25 to 30 years. If the covering needs replacing in ten, it is usually cheaper to re-roof first than to lift and refit the array later.
  • Structural capacity. Older portal frames and lightweight purlins may not have spare capacity for the added load.
  • Asbestos. Fibre cement roofs on older buildings often contain asbestos, and the duty to manage asbestos means a survey is usually needed before any work.
  • Grid constraints. A network that cannot take your export may mean an export limit, a smaller system or a reinforcement cost.
  • Ownership and consent. Tenants need landlord consent, and lease length matters for payback.
  • Planning. Most non-domestic rooftop solar in England falls under permitted development, but listed buildings, conservation areas and some flat roof arrangements need checking.

How the free survey covers feasibility

When you request a survey, we review your enquiry and call you to understand the site. If it looks suitable, we arrange a free survey with one MCS certified installer matched to the site, either in person or virtually. Your details go to that one installer only. The installer's surveyor looks at the roof, the electrical intake and your consumption, and produces a proposal that should cover the outputs listed above. There is no obligation to proceed, and you can use the findings to compare other options. You can read more on what the survey includes.

What to have ready

  • Twelve months of electricity bills, or half-hourly data if you have it
  • The MPAN from your bill and your agreed supply capacity if you are on a half-hourly contract
  • Any roof drawings, the age of the roof and details of past repairs
  • Whether you own the building or lease it, and the remaining lease term
  • Any asbestos register for the premises

If you are ready to start, use the form below to request a free survey.

Frequently asked questions

How long does a commercial solar feasibility study take?

A desktop view can be produced within days of receiving your address and bills. An on-site or virtual survey takes a few hours on site for most buildings, with the proposal following once the installer has modelled the yield and checked the supply. Larger or more complex sites, or ones needing a structural engineer or asbestos survey, take longer. Timings vary by installer and site.

Is a desktop solar assessment good enough on its own?

It is a sensible first filter, but not a basis for investment. A desktop check cannot see the roof condition, hidden shading, fragile rooflights, the state of the main switchboard or asbestos. It also relies on assumptions about your consumption unless you supply real data. Treat a desktop figure as a range and confirm it with an on-site or virtual survey before committing.

What does a feasibility study cost?

Paid feasibility studies are offered by consultants and some installers, and prices depend on the scope. Through this site the initial survey is free: we arrange it with one MCS certified installer matched to the site, and there is no obligation to proceed. Separate structural or asbestos surveys, if needed, may carry their own cost, which should be explained before any work is booked.

Can a feasibility study tell me if I need G99 approval?

Yes. Almost every commercial system is larger than the G98 limit of 16A per phase (about 11.04 kW on a three phase supply), so G99 approval from your Distribution Network Operator is normally needed before connection. The study should confirm this, check your supply capacity and flag whether export limitation or network reinforcement is likely. The DNO gives the final answer through its connection offer.

Will the study include battery storage and EV charging?

It can. If your half-hourly data shows surplus solar at midday or high evening demand, a battery may be worth modelling. If you run vehicles or plan workplace charging, that changes your daytime demand and can raise self-consumption. Tell us at the start so the installer includes them. See our pages on battery storage and EV charging for business for more detail.

Free, with no obligation

Book your free commercial solar site survey

Tell us about the site in under two minutes. We review every enquiry, call you to understand the building and your electricity use, and if the site looks suitable we arrange a free survey with one MCS certified installer matched to it.

  • On site or by video callWhichever suits the project and its stage.
  • Roof, structure, grid and energy useThe four things that decide whether solar works.
  • A clear proposalSystem size, cost range, savings and payback for your board.
  • One installer onlyYour details are not passed around a list of companies.

Want the detail first? Read how a survey works and what the survey includes.

Book your free site survey

Six quick questions, then your details. Free, with no obligation.

Step 1 of 7
Question 1 of 6: What kind of site is it?
Question 2 of 6: Do you own the building, or is it leased?
Question 3 of 6: Roughly what do you spend on electricity a month?
Question 4 of 6: Is this your first time looking into solar?
Question 5 of 6: When are you hoping to go ahead?
Question 6 of 6: What kind of survey would you like?
Where is the site, and who should we ask for?

Your details go to one matched installer only.

Book a free site survey