G98 vs G99: which grid connection route your business needs

G98 covers small systems up to 16 amps per phase, about 3.68 kW on a single-phase supply or 11.04 kW on three-phase: the installer fits the system and tells the network operator within 28 days. Anything bigger comes under G99, where the installer applies first and waits for approval before connecting. Almost every commercial solar system is a G99 project.

Updated 4 minute read

The short answer

G98 G99 fast track G99 standard
Size Up to 16A per phase (about 3.68 kW single-phase, 11.04 kW three-phase) Small installations between the two, within set limits Everything above
Process Fit, then notify within 28 days of commissioning Apply, then notify within 28 days of commissioning Apply, receive a connection offer, accept it, then connect
Typical business use A very small system on a shop or office A small roof with export capped Nearly all commercial roofs, ground mounts and carports
Effect on timeline None before installation NGED answers within 10 working days Plan around the operator's assessment and any works

Both are Engineering Recommendations published by the Energy Networks Association. Your installer prepares the notification or application; the figures below are from National Grid Electricity Distribution (NGED) and NIE Networks, checked on 3 November 2026.

G98: fit and notify

NGED describes G98 as "a simple connection procedure for fully type tested installations under 16A per phase", installed on a fit and notify basis. Its criteria include:

  • The rated output is under 16A per phase, connected at low voltage
  • Interface protection is installed and tested, and the system shuts down in a power cut
  • There is a lockable isolation switch for all phases, and a circuit diagram on site
  • The network operator is notified within 28 days of commissioning

Source: NGED micro generation (G98). For a business, G98 rarely covers more than a token array: 11.04 kW of panels on a three-phase supply is a small fraction of most commercial roofs.

G99 fast track: the middle ground

NGED runs a G99 fast track for small installations, in three categories (NGED fast track):

Category Limits Process
SGI-1 Each device no more than 16A, total no more than 16A per phase Notification only
SGI-2 Each device no more than 16A, total no more than 32A, with a G100 scheme limiting export to 16A Apply, acceptance within 10 working days, then up to 3 months to install and 28 days to notify
SGI-3 Each device no more than 32A, total no more than 60A, with a G100 scheme limiting export to 32A Apply, network study result within 10 working days, then up to 3 months to install

All equipment must be type tested and the installation must be on an existing premises. If an SGI-3 study does not meet the requirements, the application is processed as a standard G99 enquiry.

G99 standard: apply first

Most commercial systems go through a standard G99 application. NGED's guidance sets out the stages (NGED G99 connection procedures):

  1. Planning. Early talks with the operator, and if you want one, a budget estimate (a desktop figure, no site visit) or a chargeable feasibility study.
  2. Application. Systems under 50 kW apply on a shorter form (A1-1); larger ones use the standard application form with site plans, equipment data and, where used, an export limitation application.
  3. Connection offer. The operator sets out the works needed and their cost. NGED's offers are valid for 90 days, with a possible single extension of a further 90 days if you ask in writing.
  4. Construction and commissioning. For larger systems, a Power Generating Module Document is kept up to date through the build, and tests and paperwork follow within 28 days of first connection.

G99 also sorts generation into types by size. NGED's guidance gives Type A as greater than 800W and less than 1MW, and Type B as 1MW to less than 10MW. Nearly every rooftop system is Type A; the paperwork grows with the type.

What it means for your project timeline

  • Start the grid question early. The survey checks your supply, switchboard and likely route, so the application is complete when it goes in. Incomplete applications are a common cause of delay; see G99 and DNO applications.
  • Do not order equipment before the offer on a standard G99 project. The offer may come with conditions, a lower export figure or works.
  • Consider an export limit if the network is constrained. It can turn a long wait into a quicker connection; see G100 export limitation.
  • Batteries count. Storage is assessed alongside the solar, so include it in the application from the start; see battery storage.

Northern Ireland

NIE Networks uses its own versions of the same routes (NIE Networks):

  • G98/NI covers up to 16 amps per phase, 3.68 kVA single-phase or 11.04 kW three-phase.
  • G99/NI Fast Track covers up to 60 amps per phase, with individual inverters limited to 32 amps per phase and export limited to 16 amps per phase. Its parameters changed on 1 May 2026.
  • G99/NI covers everything larger.

Get the grid question answered

A free survey checks your supply and tells you which route your system is likely to need before you commit. See what you qualify for.

Frequently asked questions

What is the difference between G98 and G99?

G98 covers small, fully type tested systems up to 16 amps per phase, about 3.68 kW single-phase or 11.04 kW three-phase. They are fitted first and the network operator is told within 28 days. G99 covers larger systems: the installer applies first and connects only once the operator has approved it.

Does my business solar system need G99?

Almost certainly. A three-phase supply under G98 is limited to about 11.04 kW, which is small for a commercial roof. Some small systems can use G99 fast track instead, especially with an export limit. Anything larger needs a standard G99 application.

How long does G99 approval take?

It depends on the operator, the size of the system and the local network. NGED's fast track gives an answer within 10 working days. A standard application takes longer, and if the network needs reinforcement, the works add time. Ask your installer what they are currently seeing with your operator.

Who submits the G98 notification or G99 application?

Normally the installer, on your behalf. You provide information such as your MPAN, supply details and permission, and you sign or accept the connection offer if one is issued.

Do batteries need G99 approval too?

Battery storage connected to the network counts as generation for these rules, so it is included in the notification or application. Adding a battery later may need a new application, so include it from the start if you might want one.

Free, with no obligation

See what your business could qualify for

Find out which grants, tax relief (capital allowances) and finance options your business may qualify for, and roughly what solar could save. It comes from a free call with us and a free survey with one MCS certified installer.

Tell us about the site in under two minutes. We review every enquiry, call you to understand the building and your electricity use, and if the site looks suitable we arrange a free survey with one MCS certified installer matched to it. We match you with one of 130+ MCS certified installers across the UK, and only those who pass our checks.

  • On site or by video callWhichever suits the project and its stage.
  • Roof, structure, grid and energy useThe four things that decide whether solar works.
  • A clear proposalSystem size, cost range, savings and payback for your board.
  • One installer onlyYour details are not passed around a list of companies.

Want the detail first? Read how a survey works and what the survey includes.

See what your business could qualify for

Grants, tax relief and finance your business may qualify for, and roughly what solar could save. Six quick questions.

Step 1 of 7
Question 1 of 6: What kind of site is it?
Question 2 of 6: Do you own the building, or is it leased?
Question 3 of 6: Roughly what do you spend on electricity a month?
Question 4 of 6: Is this your first time looking into solar?
Question 5 of 6: When are you hoping to go ahead?
Question 6 of 6: What kind of survey would you like?
Where is the site, and who should we ask for?

Free site survey, no obligation. Your details go to one matched installer only.

See what you qualify for